Battery power and Electrification


How to accurately position an NMP recovery unit in a location with restricted headroom? That was the latest challenge Beck & Pollitzer UK faced as they continue to help build a greener future by supporting clients working in battery power and electrification.

This challenging project took our experts to the Midlands region of the UK and required them to engineer a custom solution—an area in which we have many, many years of experience.
The NMP Recovery unit weighed in at a neat 20,000kg. Working alongside our client and a specialist engineering team, we pre-assembled the unit on a bespoke 20m x 8m mezzanine platform. Then we used our 400-ton lifting gantry to move the fully assembled unit (total weight 45,000kg) into place.

As ever, our ability to effectively collaborate and develop innovative solutions ensured the successful and safe completion of another industrial machinery installation project. Our client’s battery industrialisation centre now has new equipment that it can use to continue making an important contribution to a more sustainable future.

Beck & Pollitzer Czech was awarded a new relocation project by a major manufacturer of electrical installation equipment.  We acted as the main contractor to relocate twelve Injection Molding Machines (IMMs) and three Computer Numerical Contro…
Beck & Pollitzer undertook another warehouse automation project for a dairy producer, which was completed successfully on time. The task included the installation of a fully automated warehouse system, which will operate at a very low temperat…
At the end of 2022, Beck & Pollitzer Czech installed a spray packaging production line for a major packaging industry client. Some of the tasks which were undertaken by our experienced team in the Czech for this installation project were: Hea…
In a recent project within the automotive and industrial manufacturing sector, a major relocation was successfully executed, involving the transfer of two critical fuel injection pump production lines. This intricate operation required the movemen…
Our client, a European automotive battery leader, sought to establish a state-of-the-art battery cell plant in France to decarbonize automotive battery production. They required a partner capable of handling the complex electrical integration and …