One of the biggest automobile manufacturers trusted us with the replacement of an underbody line including fourteen pieces of robots and ten pieces of robot bases at a welding shop in Czech.

The replacement project included electrical and mechanical dismantling, relocation of new robots in place of existing ones, connection of services and exhaust system. Some of the equipment used for the project were:

  • 1x FLT Hyster 5.5t electrical
  • 1x FLT VersaLift 40/60 with crane jib
  • 1x FLT Hyster 7.0 with a crane jib

The main challenge of this project was lifting and moving the robots over fences and some other components which required very precise work. A total of 24 operatives and 940 project hours were utilised to complete the project on time and with 100% satisfaction from the client. Safety was our main concern, and careful strategic planning was essential to ensure the work was completed safely.

Beck & Pollitzer has a proven track record of carrying out major relocation and installation projects across the globe within the automotive sector. This is backed up by our 150+ years of experience and 30+ locations worldwide. Contact us and discuss your next project!

As automotive companies require to adapt to changing markets and implement the next generation of car production equipment, existing old production lines need to be removed. For this reason, a local car producer in North Hungary contacted our Hung…
Beck & Pollitzer have completed a production line relocation for a client from the automotive industry from the Sunderland depot in the UK to the Nove Mesto Depot in Slovakia. The work involved the dismantling, palletising and packaging of equ…
Beck & Pollitzer France undertook a large international logistic project for a renowned automotive manufacturer. The goal of relocating an entire model Tooling (molds and dies) from Spain to Russia was challenging – our team had to work throug…
Beck & Pollitzer UK was contacted by a repeat client in the Automotive sector. This global company required a team to deliver an asset relocation project. The works were required in order to create space in the company’s UK facility, for both …
Beck & Pollitzer has completed the installation of advanced robotics equipment and utilities for one of India’s leading automotive companies, in Maharashtra, India. The complex project required the installation and commissioning of more than 2…