Turbine installation in France


Turbine installation in France completed by Beck & Pollitzer

Beck & Pollitzer France completed the installation of a turbine for Italian manufacturer ORC (Organic Rankine Cycle). The works involved the connection of the turbine to the main pipe connection, as well as the pressure tests and other Key modifications.

The team began the installation by unloading and positioning the different equipment that would be used for the turbine. The heaviest equipment weighed 30 tonnes, so health & safety was of the utmost priority.

One challenge our team faced was scheduling. The weight of the equipment risked leading to difficulties in positioning, which could have resulted in delay. However, this was overcome efficiently, resulting in no time being wasted in the installation process.

Thanks to the professionalism of the Beck & Pollitzer team, who were organised and highly competent throughout, the project was completed on time and to the great satisfaction of the client.

  • A long-standing partnership with leading engineering company


    A long-standing partnership with leading automation and mechanical engineering company and plant supplier for e-mobility. The successful collaboration with our global client began in 2008. Listed below are three examples of our recent projects whi…
  • Shell body line installation


    New hybrid car shell body line installation Beck & Pollitzer Czech have finished the installation of a shell body line to be used by a global car manufacturer in the production of a new hybrid car for 2022. Our dedicated crew completed a numbe…
  • Working at height safety training


    Where safety is always a top priority We don’t just talk about our commitment to safety here at Beck & Pollitzer. We take actions to ensure all our clients and employees know the importance we place on protecting our people. One of the areas w…
  • Successful installation of one of the world’s biggest automated filing cabinets


    Beck & Pollitzer thrives on big challenges, and the contract we were awarded in 2018 posed us one of our biggest. Not just in terms of the size of the automated filing system we were installing, but also because many of the 2 billion pages of …
  • Successful electrical installation for an automated warehouse


    An automated warehouse in Warrington, northwest England was the location of another successful large-scale industrial installation project by Beck & Pollitzer. This assignment required the installation of a full electrical controls system onto…
Latest Tweets

Copyright © Beck & Pollitzer Ltd. All Rights Reserved.